Government delays preceding issuance of a modification are generally excusable.
Contractor justified in not proceeding with changed work until Government issues mod to contract. George A. Fuller Co., ASBCA 8524, 1962 BCA
Government delays preceding issuance of a modification are generally excusable.
Contractor justified in not proceeding with changed work until Government issues mod to contract. George A. Fuller Co., ASBCA 8524, 1962 BCA
When the Government is required to render approvals during contract performance, any unreasonable delays in doing so will result in a compensable suspension of work. M.S.I. Corporation, VACAB 503, 65-2 BCA