Government Delay in Issuance of Changes

Posted on January 1st, 2012 by

Government delays preceding issuance of a modification are generally excusable.

Contractor justified in not proceeding with changed work until Government issues mod to contract. George A. Fuller Co., ASBCA 8524, 1962 BCA

Government Delay in Approvals and Inspections

Posted on January 1st, 2012 by

When the Government is required to render approvals during contract performance, any unreasonable delays in doing so will result in a compensable suspension of work. M.S.I. Corporation, VACAB 503, 65-2 BCA

 